What Is the Projects Dashboard?
The Projects Dashboard shows the financial health of every project you're running, one row per project. It answers the three questions project teams ask most: how much have we spent against budget, how much have we billed compared with the work actually done, and are we on track to hit our margin?
Everything sits side by side in one table: what the project was sold for, what it was budgeted to cost, what has been spent, what has been billed, and what is left. Every number is calculated as of a single date you pick, so you can see where projects stand today or exactly where they stood at last month-end.
Billing is shown two ways, with and without the money customers hold back until the job is done (retainage). Time-and-materials (T&M) projects have their own tab, because they are billed differently.
The Projects Dashboard replaces the Project WIP Dashboard, with a new name and added features: a dedicated T&M tab, Net and Gross versions of key measures, export on every table, and a reworked header.
Where to find it
Go to Dashboards → New Standard → Projects Dashboard.
💡 Tip: This dashboard has a built-in ReadMe. It is the last tab at the bottom of the screen, and the green Readme button in the header takes you straight there. It covers data sources, assumptions, controls, how to use the dashboard, and every metric calculation.
Who Uses It
Heads up on data freshness: This dashboard refreshes approximately every 15 minutes. Depending on when a change lands in the data pipeline, it can occasionally take longer, up to about an hour. It is not a live feed. Always check the Last Data Refresh timestamp in the header. Timestamps are shown in Eastern Time (ET).
⚠️ This is an operational view, not your accounting books.
The numbers are built from what is recorded in BuildOps. Your accounting system (QuickBooks, Intacct, Vista, Spectrum, and so on) remains your system of record.
If you manage projects at any level, here's how you'll use this dashboard depending on your role:
Role | How You'll Use It |
Project Manager | Check % complete, over/under billing, and cost variance on your active projects. Use the Project – Department View to see which trade is driving a project's position. |
Operations / Project Executive | Review the full project portfolio in one table. Spot projects running over budget, underbilled, or below their budgeted margin before month-end. |
Controller / Accounting | Use the As of Date for month-end review. Choose Net or Gross over/under billing to match how your company accounts for retainage, and export the table for reconciliation. |
Owner | Get a one-screen answer to "how are our projects doing?" Budget vs. actual, margin, and backlog for every project. |
Department Manager | Filter to your department to see cost, billing, and margin for your crews' share of each project. |
What's on the Page
The dashboard has one working page with three tabs, plus a built-in ReadMe.
The pages and tabs
Page / Tab | What It Is |
Projects Dashboard → Non-T&M Projects → Project View | Opens by default. One row per project for every project that is not time-and-materials, including both Quoted and Unit Price projects. They are not broken out into separate tables, but you can narrow to one or the other using the Project Billing Type filter on the table. All metrics are calculated on project totals. Use it for month-end review and over/under billing. |
Projects Dashboard → Non-T&M Projects → Project – Department View | One row per department within each project, grouped under the project. The same measures as the Project View, one level deeper. Use it to see which departments are driving or eroding a project's margin. |
Projects Dashboard → T&M Projects | One row per time-and-materials project, at the project level only. Uses T&M-specific columns: Budget Model, Remaining to Bill, Estimated Revenue, and Estimated Unbilled. Retainage and earned-revenue columns are intentionally not shown. |
ReadMe | The in-report reference guide. It sits at the back of the dashboard, and the green Readme button in the header takes you straight to it. Covers data sources, assumptions, controls, how to use the dashboard, and every metric calculation. |
The header
Element | What It Does |
Logo and account name | Shows the account you are viewing. For multi-tenant accounts, updates to the tenant selected in Account Name. If no tenant is selected, the logo and header show the first tenant alphabetically. |
Last Data Refresh / Est. Next Data Refresh | Shows how fresh the data is, in ET. The report refreshes about every 15 minutes, and occasionally up to about an hour. |
Current Date | Today's date. |
Back to Dashboard Hub | Returns you to the Dashboard Hub, the new landing page for the Standard Dashboards. |
Advanced Filters/Options | Opens a pop-up with the less-used controls: Account Name, Exclude Invoice Status, and Project Status. |
Readme | Jumps to the ReadMe page. |
The filters
Filter | Where It Lives | What It Does | Good to Know |
Account Name | Advanced Filters/Options | Lets customers with more than one BuildOps account (multi-tenant) filter to any one of them. | Appears on every dashboard, even if you only have one account. |
Exclude Invoice Status | Advanced Filters/Options | Removes invoices, and their retainage, in the statuses you select. | Affects billing and retainage figures only. Costs, budgets, and contract values are not affected. Leave blank to include everything except Void. |
Project Status | Advanced Filters/Options | Filters by project status. | Defaults to Work in Progress and Work Complete. Accepted and Closed can be added. Void, On Hold, and Bid projects are always excluded. The dropdown only lists statuses that exist in your account. |
Billing Customer | Control row (all tabs) | Limits the view to one or more billing customers. | Shared across all three tabs. |
Project Number | Control row (all tabs) | Narrows to one or more specific projects. | Shared across all three tabs. |
As of Date | Control row (all tabs) | Sets the cutoff for every cumulative metric and the period for month-to-date (MtD) metrics. | Defaults to Today. Includes everything dated through the end of the selected day. Shared across all three tabs. |
Project Department | Each tab, separately | Project View: limits to projects assigned to the selected department(s) on the project record. Project – Department View: limits to the selected department rows. | Each tab has its own copy. Filtering one tab does not filter the others. |
Budget Model | T&M tab only | Filters T&M projects to Budgeted or Legacy. | See Key Terms below. |
Estimated Margin for T&M Projects* | T&M tab only | A decimal you type in to calculate Estimated Revenue. | Required. Defaults to 0.2 (20%). See the T&M Projects section. |
Projects Dashboard header and control row: Billing Customer, Project Number, As of Date, with the Non-T&M / T&M tabs below
Advanced Filters/Options pop-up showing Account Name, Exclude Invoice Status, and Project Status defaulted to Work in Progress and Work Complete
Key Terms You'll See
New to the dashboard? Start with the first two tables. They cover what you need to read it. The third is a reference for when something needs more explanation.
Construction basics
Term | What It Means |
Contract | The total price the customer agreed to pay for the project. |
Cost Budget | What you expect the project to cost to build. The difference between Contract and Cost Budget is the planned profit (margin). |
Change Order | An approved change to the project's scope that adjusts the contract, the cost budget, or both. |
Schedule of Values (SOV) | The contract broken into line items. Contractors bill progress against these lines. |
Progress Billing / Pay Application | Construction projects are usually billed in stages as work is completed, rather than all at the end. Each stage is billed on a pay application, which shows the work completed against the Schedule of Values. |
Substantial Completion | The point where a project is finished enough to be used for its intended purpose. This usually triggers the release of retainage. |
Retainage | Money contractually held back on construction jobs and pay applications, typically 5–10% of each progress billing, until the project reaches substantial completion. It is not overdue. It just has not been released yet. |
WIP (Work in Progress) | A regular look, usually at month-end, at every open project: how much of the work is done, how much has been billed, and the gap between the two. That gap is the over/under billing position. This dashboard used to be called Project WIP. It was renamed because it is an operational view built from BuildOps data, not an accounting-grade WIP schedule. |
Accounting system (ERP) | Your system of record for financials, such as QuickBooks, Intacct, Vista, or Spectrum. This dashboard is not a replacement for it. |
Multi-tenant | A customer with more than one BuildOps account. The Account Name filter lets them choose which account to view. |
Reading the report
Term | What It Means |
% Complete (% POC) | How far along a project is, measured by how much of its cost budget has been spent. This is called the cost-to-cost method. Formula: Actual Cost ÷ Current Cost Budget. Capped at 100% for Closed projects. |
Earned Revenue | The revenue you have earned so far based on progress. Formula: % POC × Current Contract, capped at the Current Contract. |
Over/Under Billed | Compares what you have billed to what you have earned. If you have billed more than you have earned, you are overbilled: cash is ahead of the work. If you have billed less, you are underbilled: the work is ahead of the cash. Formula: Billed − Earned Revenue. Positive = overbilled. Negative = underbilled. |
Net vs. Gross | Net excludes the retainage your customer is holding back. It is what you can collect now. Gross adds open retainage back in. It is the full value of the work billed. Billed to Date, Over/Under Billed, Backlog, and Margin % each come in both versions. Pick one and stay consistent when comparing projects. |
As of Date | The most important control on the page. Every cumulative number is a sum of activity dated on or before this date, through the end of that day. Month-to-date (MtD) columns count from the first of that month through the As of Date. For example, with an As of Date of November 10, MtD covers November 1 through November 10. |
T&M Projects | Time-and-materials projects bill for time and materials as the work happens. There is no fixed contract to be a percent complete of. If T&M projects sat in the main table, every billed dollar would look overbilled. They get their own tab with columns that make sense for T&M. |
Good to know
Term | What It Means |
Quoted vs. Unit Price projects | Quoted: billed against a set contract price. Unit Price: billed by the quantity of work completed at agreed rates per unit. Both appear on the Non-T&M tabs and are not broken out separately, but the Project Billing Type filter on the table can narrow to one or the other. |
Project Ledger | The single source behind almost every number on the page. Think of it as a running journal: every budget line, change order, schedule of values line, cost, bill, and invoice on a project is a row, tagged with a category, cost type, department, and incurred date. The dashboard sums the ledger. It does not have its own private math. |
Gross Project Position | A label for each project: Overbilled, Underbilled, or Accurately Billed. Based on Gross Over/Under Billed. |
Retainage Withheld / Released / Net Retainage Receivable | Withheld is the total retainage held back on pay applications through the As of Date. Released is the total released through the As of Date. Net Retainage Receivable is Withheld − Released, the retainage still owed. It matches the project's Retainage Withheld KPI in BuildOps. |
Backlog | The contract you have not billed yet. Current Contract − Billed, in Net and Gross versions. |
Internal Change Order | A change order that moves the cost budget without moving contract revenue. It can be negative, so a project's Current Cost Budget can go down after an internal change order. |
Unclassified Cost | Cost lines with no valid cost type. A growing Unclassified number is a data-entry item, not a report problem. |
Unspecified (department) | Ledger lines with no department. They still count, but cannot be attributed to a department. They appear as an Unspecified row in the Project – Department View. |
Budget Model (T&M) | Budgeted: the T&M project has an Estimated Contract Value greater than zero. Legacy: the project was set up before this existed, or the Estimated Contract Value was left at zero. On Legacy projects, budget-based columns show blank. A zero contract value means "never set," not "free." |
Estimated Margin (T&M) | The margin you expect to earn on T&M work, typed in as a decimal (default 0.2 = 20%). Used to estimate revenue on T&M projects. See the T&M Projects section. |
How to Use the Dashboard
Set up the header and controls
Check data freshness. Look at Last Data Refresh and Est. Next Data Refresh in the header. If a number looks off, check this first.
Open Advanced Filters/Options if needed. The defaults are right for most users. Open it to choose a tenant (multi-tenant accounts), exclude Draft invoices from billing, or add Accepted or Closed projects.
Set the As of Date. Today is the default. For a month-end review, set it to the last day of the month.
Narrow by Billing Customer or Project Number if you are focused on a specific customer or project.
💡 Tip: If a project seems to be missing, check Project Status in Advanced Filters/Options first. By default, only Work in Progress and Work Complete projects appear.
Month-end close: Before a month-end review, decide whether Draft invoices belong in your close. If they do not, select Draft in Exclude Invoice Status before you read the numbers. Drafts are included by default.
Non-T&M Projects: Project View
This tab opens by default. Each row is one project, read left to right in column groups.
Column Group | Columns | What It Tells You |
Identity | Billing Customer, Project Number, Project Name, Project Status, Project Department, Project Manager, Property | Which project this is. |
Contract | Original Contract, CO Revenue, Current Contract | What you sold, plus approved change orders. |
Cost budget and hours | Original Cost Budget, CO Cost Budget, Current Cost Budget, Budgeted Margin %, Budgeted Hours, Hours Used | What you planned to spend. |
Progress | %POC, Earned Revenue | How far along the project is, and the revenue earned so far. |
Actuals | Actual Cost, Labor Cost, Material Cost, Subcontractor Cost, Equipment Cost, Overhead Cost, Other Cost, Unclassified Cost | What you have really spent, and where it went. |
Billing | Net Billed To Date, Billed Tax, Gross Billed | What you have billed. Tax is shown separately and is not included in Net or Gross. |
Over/Under | Net Over/Under Billed, Gross Over/Under Billed, Gross Project Position | Whether billing is ahead of or behind the work. |
Margin and balances | Net Margin %, Gross Margin %, Cost Variance, Budget Overrun, AR Balance (excl. Retainage), Net Backlog, Gross Backlog | Where the project is heading, and what is left to bill. |
Retainage | Retainage Withheld to Date, Retainage Released, Net Retainage Receivable, Retainage % of Contract | What the customer is holding back. |
Month-to-date | MtD Actual Cost, MtD Net Billed, MtD Gross Billed, MtD Retainage Withheld, MtD Retainage Released, MtD Earned Revenue | What happened in the As of Date's month. |
Example (illustrative): an underbilled project. A plumbing contractor is renovating a school on a $500,000 contract with a $350,000 cost budget.
Step | What You See | What It Means |
1. Contract | Current Contract is $500,000. | What the project was sold for. |
2. Cost budget | Current Cost Budget is $350,000. | What the project is expected to cost. |
3. Progress | Actual Cost is $210,000, so %POC is 60% ($210,000 ÷ $350,000). | 60% of the cost budget has been spent, so the project is about 60% complete. |
4. Earned Revenue | $300,000 (60% × $500,000). | The revenue earned so far based on progress. |
5. Billing | Net Billed To Date is $200,000. | What has been billed, excluding retainage. |
6. Over/Under | Net Over/Under = $200,000 − $300,000 = −$100,000. | The project is underbilled. The work is $100,000 ahead of the cash. That is a billing conversation to have now, before the project closes. |
Focus on risk and opportunity. In the table, look for projects with:
High Budget Overrun or negative Cost Variance: the project is tracking over budget.
High % Complete but large underbillings: revenue is earned but not yet billed (an asset at risk).
Low % Complete but large overbillings: billed ahead of the work, which signals potential future margin pressure.
Low Budgeted Margin %: the contract may be underpriced or at risk of missing margin targets.
Large Net Retainage Receivable on Work Complete projects: retainage is ready to be released and billed.
Net vs. Gross and Retainage
Most billing measures come in two versions. Net is billed without the retainage your customer is holding back. Gross adds that retainage back in.
How they relate: Gross Billed = Net Billed To Date + Net Retainage Receivable. Net Retainage Receivable = Retainage Withheld − Retainage Released.
Which one to use:
Use Gross Over/Under Billed if your accounting counts retainage as billed. This is the standard WIP basis.
Use Net Over/Under Billed if you track billing net of retainage.
The most common misread on this dashboard is comparing a Net number to a Gross number. Always check the column label.
💡 Tip: tie retainage to the project. Net Retainage Receivable matches the project's Retainage Withheld KPI in BuildOps. If you question a retainage number, compare those two first. The KPI reflects today, so check the As of Date, and remember that excluding Draft in Exclude Invoice Status also removes retainage from draft pay applications.
Non-T&M Projects: Project – Department View
Click Project – Department View. The table title reads Projects Report – Non-T&M – Department Breakdown. Each project is broken out into one row per department, grouped under the project. For example, you can see cost, billing, and margin for plumbing versus HVAC on the same mechanical project. It uses the same measures as the Project View, one level deeper.
📝 Department rows will not always add up to the project row. Budget and contract lines, and the earned-revenue cap, are calculated per department. On some projects, the departments' Earned Revenue will not sum exactly to the project's. This happens when cost is coded to a department that has no budget or contract. It affects only a very small share of projects. For project totals, always use the Project View.
Example (illustrative): A mechanical contractor's project has HVAC and Plumbing departments. All of the contract ($200,000) and cost budget ($150,000) sit under HVAC.
Row | Cost | %POC | Earned Revenue | Why |
HVAC | $60,000 | 40% | $80,000 | All of the contract and cost budget sit here. |
Plumbing | $15,000 | 0% | $0 | No plumbing budget, so %POC cannot be calculated. |
Project View | $75,000 | 50% | $100,000 | The project row uses combined cost, budget, and contract. |
The department rows add up to $80,000, not $100,000. The $20,000 gap comes from cost coded to a department with no budget.
Ledger lines with no department appear under an Unspecified row. They still count, but cannot be attributed to a department.
T&M projects do not appear in this view. T&M is project-level only.
Department Breakdown table showing a project with a Construction row and an Unspecified row
T&M Projects
Click T&M Projects. This tab has its own controls: Project Department, Budget Model, and Estimated Margin for T&M Projects*.
Most columns match the Non-T&M table. The differences:
Column | What It Shows |
Budget Model | Budgeted or Legacy (see Key Terms). |
Current Contract | For Budgeted projects, the Estimated Contract Value. |
Remaining to Bill | Current Contract − Net Billed To Date. Not clamped, so it goes negative once you have billed past the estimate. |
% of Budget Used | Actual Cost ÷ Current Cost Budget. |
Gross Profit | Net Billed To Date − Actual Cost. |
Estimated Revenue | Actual Cost ÷ (1 − Estimated Margin). |
Estimated Unbilled | Estimated Revenue − Net Billed To Date, never below zero. |
Not shown on T&M, on purpose: retainage columns, Gross Billed, Gross Over/Under, and the earned-revenue and % POC columns. T&M does not carry retainage, and cost-to-cost progress does not apply.
On Legacy T&M projects, Current Contract, Remaining to Bill, Budgeted Margin %, % of Budget Used, Cost Variance, Budget Overrun, and Net Margin % show blank.
Why the Estimated Margin control exists
On a fixed-price project, the dashboard measures earned revenue against the contract. T&M projects bill for time and materials as the work happens, so there is no contract price to measure against, and earned revenue cannot be calculated the normal way. The Estimated Margin control fills that gap. You type in the margin you expect to earn on your T&M work, and the dashboard uses it to estimate the revenue your costs should produce.
How to use it
Enter the margin your company typically expects on T&M work, as a decimal. The default is 0.2 (20%). The dashboard then calculates:
Estimated Revenue = Actual Cost ÷ (1 − Estimated Margin). At 0.2, every $1.00 of cost implies $1.25 of revenue.
Estimated Unbilled = Estimated Revenue − Net Billed To Date, never below zero.
Estimated Unbilled is a quick read on how much T&M work you have probably earned but have not billed yet. A large number points to time and materials sitting on the project that have not made it onto an invoice.
📝 Note: These two columns are projections based on the margin you enter. They are not ledger facts. Change the margin and the numbers change.
💡 Example (illustrative): An HVAC contractor's T&M service project has $40,000 in Actual Cost. With Estimated Margin at 0.2, Estimated Revenue = $40,000 ÷ 0.8 = $50,000. If Net Billed To Date is $45,000, Estimated Unbilled = $5,000.
💡 Tip: margin is not markup. Type the margin as a decimal: 0.2 for 20%, 0.3 for 30%. A 20% margin equals a 25% markup. If you bill T&M at a 25% markup and type 0.25, Estimated Revenue will be overstated: $1.00 of cost becomes $1.33 instead of $1.25. Enter the margin, not the markup.
T&M tab with a Budget Model = Budgeted project
Exporting and Scheduling
Every table has its own Export option. You can also export or schedule the whole dashboard.
Export a single table:
Hover over the table and click the ⋮ menu in its top-right corner.
Click Export.
Choose CSV, Excel, JSON, or PDF to download right away (1M-row limit), or choose Export... or Schedule exports... to send it by email.
Export or schedule the whole dashboard:
Click the folder icon in the bottom-left corner of the screen.
Click Export... to download the current view.
Click Schedule exports... to set up a recurring export (daily, weekly, or monthly) delivered to any email address.
💡 Tip: Exports reflect your current filters, including the As of Date. For a month-end snapshot, set the As of Date to month-end before you export or schedule.
Table ⋮ menu → Export showing CSV, Excel, JSON, PDF, Export..., Schedule exports...
What Data Is Included (and What Isn't)
These rules are applied at the data level. Most do not appear as controls on the dashboard, but they shape every number you see.
Rule | What It Means | Why |
Projects only | Service jobs and service agreements are excluded. | This dashboard is built for project work. Service work lives on the Service Dashboard. |
Default statuses: Work in Progress and Work Complete | Accepted and Closed projects are hidden unless added in Advanced Filters/Options. Void, On Hold, and Bid are always excluded. | Keeps the default view focused on active projects. |
T&M is split out | The Non-T&M tabs exclude T&M projects. The T&M tab includes only T&M. This is a built-in table filter, not a control you can change. | Fixed-price progress math makes every T&M dollar look overbilled. The built-in filter means nobody can accidentally flip it. |
Void invoices and void pay applications are always excluded | They never appear in billing or retainage. | They do not represent real billing. |
Draft invoices are included by default | Use Exclude Invoice Status to remove them. Excluding Draft also removes retainage from draft pay applications. | Matches the Projects Finance tab in BuildOps. |
Payments and tax are excluded from billed amounts | Net and Gross Billed are pre-tax and exclude payment lines. Billed Tax is shown separately. | A payment is not billing, and tax is not revenue. |
Deleted records are excluded | Deleted records never appear and cannot be brought back into the report. | Shows only the live set of project lines. |
Lines with no incurred date drop out | A ledger line with no incurred date cannot be placed on a timeline, so it falls out of every As of Date calculation. This is rare. | The As of Date filter reads one incurred date per line. |
Future-start budgets show $0 | Original budget lines are dated by the project start date. A project with a future start date shows $0 original budget until the As of Date reaches the start date. Change order budgets are dated by their approval date, so they are not affected. | Budgets only count once they are in effect. |
Labor timesheets are included in cost | Incurred Time entries are included in project cost totals. | Labor is a real cost on the project. |
If You Used Project WIP
The Projects Dashboard replaces the Project WIP Dashboard. Here is where things moved:
If You Were Using... | Now Use... | What Changed |
Project WIP Dashboard | Projects Dashboard | New name, reworked header, and the ReadMe moved to the back. |
Project WIP's single project table | Non-T&M → Project View | T&M projects moved to their own tab. |
(not available before) | T&M Projects tab | New. Budget Model, Remaining to Bill, Estimated Revenue, and Estimated Unbilled. |
(not available before) | Net vs. Gross columns | Billed, Over/Under, Backlog, and Margin % now appear in both versions. |
Project Cost Type filter | Project Analysis Dashboard → Project Budget vs Actual | Removed. Cost-type analysis lives in Project Analysis. |
Old Invoice Status filter | Exclude Invoice Status (Advanced Filters/Options) | Replaced. You choose which statuses to remove from billing. |
How It Fits With the Other Standard Dashboards
If You're Asking... | Open... | Why |
Where does every project stand right now, or at month-end? | Projects Dashboard (this dashboard) | One row per project. Budget, cost, billing, margin, backlog, and retainage as of any date. |
What happened on this project, and when? | The month-by-month financial timeline for a single project. | |
Budget vs. actual by cost type, cost code, or phase | Project Analysis Dashboard → Project Budget vs Actual | Drillable below the project level. |
The same questions for service work | Service Dashboard (formerly Service WIP) | The Projects Dashboard covers projects only. |
Frequently Asked Questions
Frequently Asked Questions
Q: What happened to Project WIP?
A: Project WIP is now the Projects Dashboard. It was renamed because it is more than a WIP schedule: it is your one place for budget, cost, billing, margin, and backlog on every project. It also gained a dedicated T&M tab, Net vs. Gross columns, per-table export, and a new header.
Q: Why don't I see my project?
A: Open Advanced Filters/Options and check Project Status. By default, only Work in Progress and Work Complete projects show. If yours is Accepted or Closed, add that status and it will appear. If it is a T&M project, it will be on the T&M tab. Also check that the Billing Customer, Project Number, and Project Department filters are not narrowing it out.
Q: Why don't the department rows add up to the project row?
A: Department rows are calculated department by department, so on a small number of projects they will not add up exactly to the project total. This happens when cost is coded to a department with no budget or contract. For the project-level number, use the Project View. Use the Department View to see which trade is driving the position.
Q: Why doesn't the margin match our accounting system?
A: Cost and billing should tie to what is posted in BuildOps. Net and Gross Margin % are calculated on what has been billed so far: (Billed − Actual Cost) ÷ Billed. Differences from your accounting system can come from timing and how retainage is handled. To reconcile, export the table and compare cost, billing, and retainage column by column.
Q: Should I use Net or Gross?
A: Use Gross Over/Under Billed if your accounting counts retainage as billed, which is the standard WIP basis. Use Net if you track billing net of retainage. Either works. Just pick one and stay consistent when you compare projects.
Q: Why did my cost budget go down?
A: An internal change order can reduce the cost budget without changing the contract. For example, an electrical contractor has a $150,000 contract with a $120,000 cost budget, a 20% Budgeted Margin. A negative $5,000 internal change order drops the Current Cost Budget to $115,000. The contract stays at $150,000, so Budgeted Margin % rises to about 23.3%. Check the project's change orders in BuildOps for an internal change order with a negative amount.
Q: Why is my T&M project showing blanks?
A: That project uses the Legacy budget model, which means it was set up before the Budgeted model existed or its Estimated Contract Value is zero. Budget-based columns like Remaining to Bill and % of Budget Used stay blank. Once an Estimated Contract Value greater than zero is entered, the project moves to the Budgeted model. These columns also need a cost budget on the project to calculate.
Q: Why is Remaining to Bill negative?
A: On T&M projects, Remaining to Bill is Current Contract − Net Billed, and it is not clamped at zero. A negative number means you have billed past your estimated contract value. It is a signal to revisit the estimate with the customer.
Q: Why is cost showing as Unclassified?
A: Unclassified means those cost lines do not have a valid cost type. Typos in cost types push cost into Unclassified. It is a data-entry item, not a report issue. Fixing the cost type on those lines moves them into the right column after the next refresh.
Q: Where did the Cost Type filter go?
A: The Project Cost Type filter and the old Invoice Status filter were removed. For cost-type analysis, use the Project Analysis Dashboard's Project Budget vs Actual page. It is built for drilling into cost type, cost code, and phase. On this dashboard, you can still see actual cost broken out by type in the table columns.
Q: Why does my new project show $0 budget?
A: Original budget lines are dated by the project start date. If the start date is in the future, the budget shows $0 until the As of Date reaches the start date. For example, a sprinkler retrofit with a start date of December 1 shows $0 budget with the As of Date set to a day in November. Once the As of Date reaches December 1, the budget appears. Change order budgets follow their approval date, so an approved change order can still show even when the original budget is $0.
Q: Why does the header show a different company than I expected? A: For multi-tenant accounts, the logo and account name in the header follow the Account Name filter. If no tenant is selected, the header shows the first tenant alphabetically. Open Advanced Filters/Options and pick the account you want in Account Name. The logo and header will update to that account.





![Advanced Filters/Options pop-up showing Account Name, Exclude Invoice Status, and Project Status defaulted to Work in Progress and Work Complete]](https://downloads.intercomcdn.com/i/o/pz6cvnbp/2820847201/6e1de51e2499ebfabb15f0727e2a/image.png?expires=1795355100&signature=e8b6cbfa6c65b5398b72a1c973290da2c31f51b01ee9e587c7c07d405d0649fc&req=diglFsF6moNfWPMW1HO4zRsFYbG6UMsYuARn%2FXmay2gvnlazeJC3sVVfXaR4%0AYW9yHgdCoStrp9Ij5C4%3D%0A)